Working is progressing slowly due to rains. Not much remains to be complested: the main cable and the penstock.

Karlapat has an amazing banyan tree near the micro hydro site.

The 110-or-so home village also has amazingly sweet kids...non-stop gigglers.

Rains have washed out the road in front of the power house.

The system has 2 pumps as turbines designed for an output of 10-25 kW.


Laying the penstock should have been one of the first steps in implementation, but we could not manage the schedule...



2 comments:
Hi, dipti.... your and my area of interest of work seem to be the same.
I think there is lots that we can share.
-Vishakha
Feel free to write me at info@gramvikas.org