Working is progressing slowly due to rains. Not much remains to be complested: the main cable and the penstock.

Karlapat has an amazing banyan tree near the micro hydro site.

The 110-or-so home village also has amazingly sweet kids...non-stop gigglers.

Rains have washed out the road in front of the power house.

The system has 2 pumps as turbines designed for an output of 10-25 kW.


Laying the penstock should have been one of the first steps in implementation, but we could not manage the schedule...